Design

of process units and offsite facilities

Design works performed

AO IPN is a general designer of Krasnodar refinery - Krasnodarekoneft ZAO, Kaliningrad petrochemical complex, Afipka NPZ OOO, etc.

Design works have been performed for Moscow Refinery OOO, Turkmenbashinsky Refinery, Gazprom Neft-Omsk Refinery OAO, Slavneft-Yaroslavnefteorgsintez OAO, Lisichansk refinery, Tuapse Kemoil ZAO, Naftan OAO (Belarus), Antipinsky Refinery ZAO, Kaliningrad petrochemical complex, Mariysky refinery OOO, Afipka NPZ OOO, etc.


Jobs complited (in Russian)

Examples of projects

KINEF OOO». Revamping of crude distillation unit (CDU-6) with replacement of rectification columns in 2012-2013.

KINEF OOO.
Revamping of crude distillation unit (CDU-6) with replacement of rectification columns. 2012-2013.

«Antipinsky NPZ ZAO».
Crude distillation unit (CDU-2). New construction. 2007-2010

Afipka NPZ OOO.
Gallery-type rack for oil unloading/diesel fuel and mazout loading. Capacity up to 10 million tpa. New construction. 2011-2013

ООО «Afipka NPZ OOO».
Renovation of crude distillation unit 22/4. 2012-2013.

Afipka NPZ OOO.
Renovation of SPGK (integrated treatment of gas and gas condensate) unit, with capacity gain from 1.8 to 2.5 million tpa. 2011-2012.

KNPZ-KEN ZAO».
Rectificate cooling unit of columns K-1 and K-2.

GAZPROMNEFT AO – Moscow Refinery». Gas distribution station. Upgrading. 2015-2017.

GAZPROMNEFT AO – Moscow Refinery.
Gas distribution station. Upgrading. 2015-2017

NOVATEK-Ust-Luga OOOSGC fractionation unit. Final cooling unit. Technical upgrading. 2015г.

NOVATEK-Ust-Luga OOO.
SGC fractionation unit. Final cooling unit. Technical upgrading. 2015г.

Republic of Kazakhstan. Shymkent refinery. High-temperature transfer pipeline for transferring of two-phase flow at transonic speeds. 2016.

Republic of Kazakhstan. Shymkent refinery.
High-temperature transfer pipeline for transferring of two-phase flow at transonic speeds. 2016.